Over the years, many projects have been undertaken in the downtown area to improve the economic vitality and the pedestrian experience.  Recently within the city as well as across the country, downtown alleys have been identified as potential areas to further develop multi-modal transportation as well as provide new business opportunities for downtown properties. 

 

February 16, 2012 - Construction slated to begin March 5, 2012; two public meetings scheduled.

December 21, 2011 - The alley design has been completed and the project put out to bid.

March 4, 2011 - Public Meetings Scheduled - Your input is requested.

November 12, 2010 - Conceptual Design Phase Complete

October 20, 2010 - Public Forum 2

September 22, 2010 - Public Forum 2 - Wednesday, October 13, 2010, from 6:30 to 8:00 in the Longmont Library Conference Rooms A & B

July 6, 2010 - Public Forum 1 - July 22, 2010 from 6:00 to 7:30 in the Longmont Library Conference Rooms A & B

June 17, 2010 - Alley Project Update - The design consultants have been gathering existing alley information including electrical services, parking lot configurations, breezeway details and drainage patterns. The design charette will be held June 30, 2010 from 8:00 am to 1:00 pm.

April 26, 2010 - Project Overview - To address these issues the Public Works & Natural Resources Department in coordination with the Longmont Downtown Development Authority (LDDA) is underway with a Capital Improvement Project to improve the downtown alleys. 

April 26, 2010- Weekly Updates - This site includes a calendar of events, an on-line survey, an area to provide comments/suggestions as well as a “What’s New” area that provides updates for weekly activities.