Additions -- Inspections
CALLING
FOR INSPECTIONS
FOOTING
INSPECTIONS
FRAMING INSPECTIONS
INSULATION INSPECTIONS
FINAL INSPECTION
Calling for Inspections
Requests for inspection are recorded on the Building Inspection Selectron
system by calling (303) 774-4595. You will need your permit number and inspection
card. Follow the voice mail prompts. Inspections are usually made on the following
day, it is wise to anticipate when they need to be made to prevent delays.
NOTE: No inspection will be made on subcontracted work done by an unlicensed subcontractor.
You should not proceed to cover-up any work that has not been inspected.
You SHOULD NOT schedule any concrete or other major work for the same day
as the inspection to avoid costly problems. Inspections must be called in
the day before needed in order to efficiently schedule and route the Field
Inspectors.
Please have all animals including dogs under control and not in the areas
to be inspected. Inspections may not be made if there are animals running
loose and a re-inspection fee may be required if this occurs.
The final inspection is the last step in the inspection process, and is your
certification that the work has been satisfactorily completed according to
building code.
Back
to Top
Footing
Inspections
- Site address posted during entire construction.
- Inspection Record Card in plain sight.
- Approved plans and site plan on site.
- Lot Lines clearly marked with string lines or otherwise.
- Footing/Foundation forms and reinforcement in place.
Back
to Top
Framing
Inspections
- Inspection Record Card posted on site.
- Approved plans on site.
- Engineer stamped and signed truss plans.
- Trash enclosure on site to prevent litter and blowing trash.
- Plumbing, Mechanical and Electrical roughed in (if any).
- All framing, fire blocking and bracing done.
- Plumbing/Mechanical/Electric
- Underground Plumbing, Gas Line, Rough Plumbing, Mechanical and Electrical
roughed in.
Back
to Top
Insulation
Inspections
- Inspection Record Card posted on site.
- Any other work that may be covered up inspected and approved.
- Insulation and Vapor retarder installed.
Back
to Top
Final Inspection
- Inspection Record Card posted on site.
- All Plumbing, Heating, Electrical and Framing work done and approved.
- Final Grading and paving including any required driveways done.
Back
to Top
-->